Timeline

 Project timeline_2013_SEW


Project timeline

  • Planning phase: Completed by June 2010
  • Design phase: July 2010 to December 2013 
  • Construction phase: April 2014 to December 2016

The project will require several actions by the water district Board to complete the anticipated work. Below is a list of the actions and when these items are estimated to be brought to the Board for approval.

Adopt Planning Study Report and authorize staff to proceed with design: June 2010

Certify Final Environmental Impact Report and Approve Project: December 2013