|
RETURN
TO TABLE OF CONTENTS
VI. CEQA QUESTIONS
The California Environmental Quality Act (CEQA) requires that an EIR address certain general questions
that bridge the discussion of individual technical topics. This Chapter addresses those statutory issues.
A. GROWTH INDUCING ASPECTS OF THE PROPOSED
PROJECT
CEQA guidelines state that growth-inducing impacts are defined as ways
in which the proposed project could foster economic or population growth, or
the construction of additional housing, either directly or indirectly, in the
surrounding environment. The concept of growth inducement also includes the
characteristic that some projects may encourage and facilitate other activities
which could significantly affect the environment, either individually or
cumulatively.
The proposed program is the continuation of existing routine
maintenance activities performed by the District. The purpose of the
maintenance project is to maintain the District channels to be able to carry the
100-year (1%) flood, or existing design, and to maintain the channel conditions
upon which the Federal Emergency Management Agency (FEM.) flood
insurance mapping is based. Maintenance activities do not increase the amount
of land that has flood protection and therefore do not alter the land use or
economic constraints to the surrounding flood plain. Likewise, the purpose of
the District's ten canals is water conveyance, which does not increase growth
potential. Since the District's activities only maintain the infrastructure
supporting existing and planned land uses, the District's maintenance activities
are not growth-inducing.
Minor routine maintenance activities as listed in the Project Description
do not increase the population-serving capacity of the District's facilities, and
are therefore not growth-inducing.
B. SIGNIFICANT, IRREVERSIBLE ENVIRONMENTAL CHANGES
The proposed program is the continuation of ongoing sediment removal,
vegetation management and bank protection activities that have been carried out
by the District for many years. The need for ongoing routine maintenance
activities has resulted from land use change around and from past modifications
to once natural channels first done to support agriculture, and later to provide
flood protection and to accommodate transportation corridors for urban
developments on the valley floor and low foothill areas of Santa Clara County.
Agricultural modifications included clearing of vegetation, stream
straightening, and diverting water from channels. Flood control modifications
included straightening streams and installing concrete lined-sections, culverts,
and construction of levees.
In most work reaches, sediment removal, vegetation management and
even bank protection are ongoing maintenance processes, and the facilities will
not function as intended without the maintenance.
Over-steepened banks are prone to failure and need frequent armoring
and other stabilization. Ongoing regular maintenance compensates for the
unstable conditions in the channels that compromise their flood capacity or
result in property damage (bank failure) from floods. The maintenance program
did not create the conditions that led to the need for maintenance, but once
created, modified channels in the District require routine maintenance to protect
surrounding properties from flood damage. The proposed multi-year project
helps the District provide long-term protection from flooding.
The ongoing nature of maintenance means that impacts identified in the
EIR will tend to persist as long as the maintenance program continues. Some
of the effects are judged to be reversible if maintenance were discontinued.
The structures created by bank protection can be considered essentially
permanent. Chapter IV.B., Biology identifies hardscape installation for bank
protection; as having the potential to have cumulative, significant, irreversible
environmental changes: Although implementation of the BMPs would reduce
the adverse impacts, habitat would be lost or reduced in value resulting in
residual impacts . The actual amount of hardscape versus softscape to be
installed by future bank protection cannot be projected because the conditions
of each site and resulting design vary greatly and cannot be predicted. The
cumulative impacts from bank protection would thus remain significant and
unavoidable.
Other biological impacts remain significant even after application of
mitigation measures: resuming herbicide use in the Pajaro River Basin, thus
holding vegetation to a lower successional stage, and fragmentation of habitat
caused by breaking the linear stream corridors into smaller pieces. Since at this
time it is unknown the extent of impacts caused both of these practices, these
impacts are considered significant even after mitigation. However, both of
these practices do not result in irreversible changes, as the impacts would
disappear if the practices were discontinued.
C. EFFECTS FOUND NOT TO BE SIGNIFICANT
Effects found not to be significant in the Initial Study in conjunction with
the Notice of Preparation were effects on agricultural resources, mineral
resources, population and housing, transportation and traffic, public services,
and utilities/service systems.
Air quality was found not to be significant in the Initial Study but is
addressed in the Program EIR to incorporate the standard construction dust
abatement mitigation measures required by the Bay Area Air Quality
Management District as Best Management Practices.
D. CUMULATIVE IMPACTS
CEQA Guidelines state that "an EIR shall discuss cumulative impacts of
a project when the project's incremental effect is cumulatively considerable"
(§15130). A cumulative impact consists of an impact which is created as a
result of the combination of the project evaluated in the EIR together with other
projects causing related impacts. The discussion of impacts contains a list of
past, present, and probable future projects producing related or cumulative
impacts, including those projects outside the control of the agency. The
discussion of cumulative impacts should focus on the cumulative impact to
which the identified other projects contribute rather than the attributes of other
projects which do not contribute to the cumulative impact.
There are two types of cumulative discussion that are addressed in this
section: 1) activities within the purview of the proposed SMP; and 2) activities
which either are proposed by the District (such as Capital Improvement
Projects) or activities attempted by others that may affect streams in the District
(see Table II-10, Other Future District Projects in Creeks).
The Program EIR is explicitly directed to assess the cumulative impacts
of separate maintenance activities spread over space and time. Thus, the
cumulative impacts of the planned Program are discussed under the individual
environmental factors (Chapter IV) where cumulative impacts are significant
or potentially significant, or otherwise relevant: geomorphology; biology; land
use; hazards and hazardous materials; and cultural resources. The
environmental setting for evaluating the impacts of maintenance reflects the
cumulative, historic impact of land use encroachment, land use change, and
modification of creeks in the District.
1. Cumulative Impacts of the SMP
As stated in the Project Description, most of the individual sediment
removal and vegetation management activities repeatedly take place on the
same reaches of District channels. These reaches are the portion of the District
most affected by past urbanization and by the geomorphological factors that
cause sediment deposition or erosion. Vegetation management is usually an
adjunct to sediment removal, particularly in the intervening years between
treatment. Bank protection and other minor activities can occur anywhere
within District jurisdiction; however, it historically has occurred in cities and
semi-rural foothills of the Santa Clara Valley.
As stated in IV-B Biology, under the approach adopted by the District for
the proposed SMP, any removal of wetland or riparian vegetation associated
with the SMP is considered cumulatively significant. Implementation of the
BMPs would reduce the adverse impacts of the SMP caused by removing
wetland and in-stream riparian vegetation; however, residual impacts would
primarily be associated with fragmentation of wildlife habitat. Although
residual impacts may be considered insignificant when reviewed on an
individual project basis, when evaluated on a program basis, there is the
potential for significant, cumulative impacts.
The placement of additional hardscape within stretches of vegetated bank
may also contribute to significant cumulative impacts. Placement of hardscape
is a permanent change that can contribute to the increasing fragmentation of the
natural bank landscape, which can affect wildlife that depend on the stream
corridors. Increasing the amount of hardscape along a channel reduces the
amount of cover available to wildlife traversing these reaches and may make
them vulnerable to predation.
There are potential cumulative environmental impacts associated with the
mitigation projects, such as Los Capitancillos freshwater wetland creation and
Pond A-4 tidal wetland restoration, which are being done to support the SMP.
Project specific environmental impacts of the mitigation projects will be
addressed as part of the specific CEQA documents that will be prepared for all
mitigation projects.
2. Impacts From Proposed Mitigation Projects
The SMP includes a compensatory mitigation package to compensate for
significant residual impacts. This mitigation is described in detail in Chapter
5 of the SMP. There are potential cumulative environmental impacts of the
mitigation program which will be addressed as part of the Mitigation and
Monitoring Program to be prepared prior to completion of the Final EIR or
under specific CEQA documents to be prepared for certain mitigation projects
(e.g. Pond A-4 and Los Capitancillos). This section summarizes what is
currently known about potential environmental effects of these mitigation
projects and how these will be resolved. All environmental effects are expected
to be resolved, therefore, no cumulative effects along with the SMP work
activities will occur.
Coyote Lakes Park Site 10A
The project will potentially require fill in Waters of the U.S. in the
existing percolation pond, (an impoundment of Coyote Creek) gravel pond or
creek for water control structures. Construction of water control structures or
other site features may also result in removal of riparian forest, scrub or
wetland vegetation. These impacts can likely be mitigated by post-construction
restoration at the site of the impact or by providing new habitat within the
wetland mitigation project.
Steelhead trout and fall-run chinook salmon may be present in the
adjacent reaches of Coyote Creek. Fish could become stranded within the
wetland if they were to enter the wetland via the water inlet connection with the
percolation pond. Therefore, measures will be taken to limit transmission of
fishes between the existing percolation pond and the mitigation wetland (such
as installation of a fish screen on the water inlet structure).
Potential construction-related impacts to water quality (i.e. increased
sediment) in the gravel pond or creek would be avoided by taking measures to
limit turbidity during construction. Once constructed, water flowing out of the
wetland could potentially increase stream or gravel pond temperature or
turbidity. If this is found to pose a potentially significant impact, measures to
avoid this effect will be taken. Potential measures include but are not limited
to placement of the outflow structure away from the stream or gravel pond or
management of outflow timing and amount.
No take of Red-legged frog habitat is expected, but surveys will be
conducted prior to construction to avoid any potential construction related
impacts to individuals.
Western pond turtle breeding habitat could be affected. Impacts to turtle
breeding would be avoided by conducting surveys in the immediately adjacent
section of creek to determine if turtles use habitat in the vicinity of the project
area. If turtles are present, measures to avoid impacts to turtle nesting would
be taken such as avoiding construction during the nesting season or installing
exclusion fences to prevent turtles from nesting on-site during construction.
Suitable Burrowing Owl nesting habitat may be present, however the
likelihood of this is small due to the large trees that border the site and provide
habitat for Burrowing Owl predators. Pre-construction surveys will be
conducted to determine if Burrowing Owls are present. Occupied areas will be
avoided or off-site compensation may be required.
Several special-status songbirds and raptors could potentially breed on
or adjacent to the project site. Their presence would be determined by pre-construction surveys within the breeding season. A construction-free buffer
around any active nest would be established with width determined by a
qualified biologist consistent with the District's most recent nesting migratory
bird procedures.
A potential increase in flood hazard to existing infrastructure, including
Highway 101 is unlikely but will be further investigated during the project
design phase to determine with more certainty.
Cultural resources are known from nearby locations on Coyote Creek.
If present on the mitigation site, excavation could result in a potentially
significant impact. Prior to final design and construction, a qualified
archaeologist will assess the site to determine the likelihood of project impacts
to cultural resources. Measures will be taken to avoid, minimize or compensate
for any identified significant impacts.
Church Pond Number 2 Wetland Mitigation Site:
This reach of Llagas Creek has limited potential to be a migratory
corridor for steelhead trout. This potential will be further evaluated during the
project's individual CEQA review. If necessary, the water diversion structure
will be designed to allow for fish passage throughout the year, by installation
of a fish ladder or other means, thus avoiding impacts to migrating steelhead.
Fish could be transported via the water intake structure between and
Llagas Creek and the off-stream percolation ponds. A fish screen or other
design feature will be installed to avoid this impact.
Construction of a diversion structure within Llagas Creek will constitute
fill in Waters of the U.S., and may result in removal or alteration of riparian
woodland or wetland habitat. This potential impact will be determined during
the design phase CEQA evaluation. Avoidance, minimization and mitigation
measures will be implemented as needed to reduce this potential impact to a
less-than-significant level.
Los Capitancillos Freshwater Wetland Project
The proximity of the Los Capitancillos Freshwater Wetland Mitigation
Project to Guadalupe Creek introduces certain biological constraints to the
project including minimizing impacts to existing riparian habitat and avoiding
thermal impacts to salmonids. Mercury-containing sediments are also known
to be present in the Guadalupe Creek drainage as a result of historic mining.
Soil testing results indicate that total mercury concentrations exceed sediment
screening criteria for wetland cover in some areas. The project team plans to
resolve issues related to the proximity of the project site to Guadalupe Creek
and the presence of mercury-containing sediments as follows:
· The overflow structure will be designed to minimize impacts to
the riparian habitat;
· Discharges to Guadalupe Creek will be limited to the minimum
necessary to prevent flooding of upland areas, and timed to
minimize thermal impacts to salmonids;
· Soils excavated from the project site will be handled according to
guidance provided by Regional Water Quality Control Board staff
with respect to mercury contamination; and
· The wetland area will be over-excavated and lined with a layer of
clean topsoil to minimize mercury methylation.
Pond A-4 Tidal Wetland Restoration Project
The Pond A-4 Tidal Wetland Restoration Project (Pond A-4 Project) will
provide 30-acres of mitigation for impacts of the Stream Maintenance Program
to tidal wetlands. Potential significant impacts to biotic resources and regulated
habitats associated with the Pond A-4 Project will be identified during the
CEQA evaluation for the project. Alternatives for avoiding, minimizing or
mitigating the potential significant impacts will also be determined during the
planning study for the Pond A-4 Project. Preliminary analyses, however, have
identified a number of potential impacts that may result from the restoration of
the salt pond to tidal wetland.
Potential impacts to water quality may occur during construction from
the release of inorganic and organic hazardous substances occurring at the site
and in imported sediment. Phase I and II Hazardous Substance Liability
Assessments (HSLA) have been completed at the site. A Phase III investigation
will be done in the planning study phase. Levee soils, pond perimeter
sediments and groundwater were sampled and analyzed. In both levee soils and
pond perimeter sediments, levels of arsenic (and one sample of copper) were
detected in excess of Sediment Screening Criteria for Cover Material.
Sediment Screening Criteria for Noncover Material was not exceeded in any of
the samples. In the groundwater, diesel fuel, antimony, lead, nick and copper
were detected in one or more of the samples; no volatile or semivolatile organic
compounds were detected in any samples. Mercury was tested only for its
elemental form. The findings of the Phase III HSLA will determine what
remedial measures are appropriate. Depending on the results of the Phase III
HSAL, it may be possible to reduce the impacts of construction on water
quality to less than significant through the implementation a project-specific
soil and water quality best management plan during construction. In the event
that dredged sediments are imported to raise the pond bottom elevation, they
will be tested and selected in coordination with the U.S. EPA and the San
Francisco Bay Regional Water Quality Control Board to ensure that they are
suitable for re-use in aquatic system based on chemical and biological testing.
The project has the potential to temporarily and permanently impact
wildlife species. During wildlife surveys of the pond between 1999 and 2001,
82 species of birds, two species of mammal (Ground Squirrel and Black-tailed
Jackrabbit) and two species of fish (Yellowfin Gobie and Longjaw Mudsucker)
were recorded. Three Federal special-status bird species and 21 California
Species of Special Concern were among those found at the pond. Temporary
impacts to wildlife may occur during construction. Best management practices
will be used to avoid or minimize construction impacts and may include
measures such as avoiding work during the breeding season. The project will
have permanent impacts to some wildlife species due to the habitat conversion
from open water to wetland, but these impacts may not be significant. The
conversion will ultimately favor wetland-dependent species over those species,
such as diving ducks, that use deeper open water habitats. Finally, the project
may result in erosion of brackish or salt marsh habitat located down slough of
the project site. Wetland erosion may occur because of the increased tidal
prism after the site is opened to tidal flows. The nature of the impacts and
mitigation measures will be addressed in subsequent documents.
It will be necessary to consider regional flood protection issues in the
hydraulic modeling for the project to insure that the restoration design does not
impact the flood conveyance of nearby streams. The analysis will include an
evaluation of an alternative to raise the bayfront levee and other measures to
protect the adjacent upland areas from flooding.
An existing spine trail of the Bay Trail is located on the southern levee
of Pond A-4. Because of concerns regarding the impacts of adjacent
recreational use on wildlife, it will be necessary to evaluate these impacts.
Future analyses will consider a variety of measures that would attempt to
balance public access and wildlife protection, such as limiting public access
during nesting season or other appropriate times of year; limiting access to
those activities, such as wildlife observation or environmental education, that
are compatible with wildlife; and providing buffers between trails and high
quality wildlife areas.
The restored site will provide habitat for invasive or nuisance species that
occur in brackish tidal marshes and adjacent transitional areas and uplands.
The invasive plant species, perennial peppergrass, has the potential to
substantially impact wetlands by altering habitat structure or substantially
reducing populations of native species. A major commitment will be needed
to control the spread of peppergrass and others invasive species. In addition,
it will be important to address the potential for providing habitat for mosquito
species that cause human health concerns. Input from the local vector control
district will be sought to ensure the design takes vector concerns into
consideration.
Stream and Watershed Protection
Stream and Watershed Protection comprises two elements: 1) land
acquisition; and 2) projects to restore or manage stream resources on acquired
land. No significant impacts are expected to be associated with the land
acquisition element. Restoration or management projects could result in
potentially significant impacts due to the sensitive nature of stream habitat.
Restoration or management projects will be identified on a site by site basis as
land is acquired, and will vary based on site characteristics. The types of
projects to be done is not known at this time, and therefore, the nature of the
potential impacts is not known. Each project will be evaluated for potential
impacts, and will be subject to CEQA compliance. Measures will be taken to
avoid, minimize or compensate for potentially significant impacts.
Giant Reed Control Component
The Giant Reed Control component consists of the strategic removal of
approximately 125 acres of Giant Reed (Arundo donax) on target streams
throughout Santa Clara County. The removal of the non-native species would
be followed up by revegetation with appropriate native species in areas where
natural revegetation is not likely to occur.
The potential impacts associated with the removal Arundo donax are as follows:
•Potential loss of nesting habitat in areas where large monocultures of
Arundo are removed.
•Potential loss of Shaded Riverine Aquatic habitat in areas where large
monocultures of Arundo are removed adjacent to a stream.
•Potential increase in water temperature due to loss of overhanging
growth in areas where large monocultures of Arundo are removed
adjacent to a stream.
•Overall increased use of specific herbicides as a control mechanism
within the program.
The use of Arundo as habitat has been studied to some degree but
extensive published literature does not exist at this time. All evidence indicates
that Arundo donax provides neither food nor habitat for native species of
wildlife (Bell, G. 1997 Ecology and Management of Arundo donax, and
approaches to riparian habitat restoration in Southern California). The same
study cites earlier studies that show that Arundo donax lacks the canopy
structure necessary to provide significant shading of bank-edge river habitats,
resulting in warmer water than would be found with a native gallery forest of
cottonwood or willows. Anecdotally, the findings have been similar. No
appreciative habitat use of Arundo by native species has been found. The
exception has been the use of Arundo for nesting by two species of herons in
Santa Clara County. District biologists reported nesting in stands of Arundo by
Black-Crowned Night Heron and Green Heron (Ryan comment, 2000).
The potential loss of nesting habitat is a temporal loss that can be
reduced through a series of Best Management Practices in areas where this
could be a concern. By timing activities to avoid the nesting season and
through surveys, impacts from actual work can be reduced to less than
significant. In areas where the predominant species is Arundo and no other
habitat is available, removal can be phased over a number of years with
revegetation occurring in the interim to replace the any temporary habitat
losses.
Both the literature and anecdotal information point to little or no impacts
to water temperature or Shaded Riverine Aquatic values from the removal of
Arundo donax. In areas where the predominant stream-side vegetation is
Arundo, BMPs such as phased removal and revegetation can again be
implemented to reduce any potential impacts to less than significant.
The increased use of the herbicide, glyphosate, in both terrestrial and
aquatic formulations is a necessary component of this program. This herbicide
is currently used in routine vegetation management and is discussed extensively
within this environmental document. As the use proposed is consistent with
current practices and represents no changes other than the amount of material
used at a program level, the impact is not considered significant. Further, the
fact that the Arundo removal program is being implemented over a period of
more than ten years implies that any increase in herbicide use would have
impacts lessened by the extended period of time.
3. Cumulative Impacts of Other Activities Affecting District Channels
Additional actions by the District and many others are taken into account
for the cumulative analysis where relevant. The District is currently planning
and designing several flood protection projects (Table II-10). In each case,
these capital improvement projects are subject to an environmental review and
will as necessary mitigate incremental impacts on the channels to levels of
environmental insignificance. Therefore, any potential cumulative effects will
be avoided or mitigated by the future CIP projects during their CEQA review.
The Project Description describes how CIPs are not part of the proposed
SMP and will analyze long-term maintenance impacts under separate future
environmental review. Any environmental effects of new CVP will be
compared to the conditions currently evaluated for that reach of stream under
the SMP. New mitigation for CVP will only be required if there are impacts
for the same reach of creek that require new mitigation in addition to the
package contained in this document and the SMP.
The Total Maximum Daily Load (TMDL) program is a District
cumulative activity, but future TMDL will not increase environmental impact
of routine maintenance. This program will reduce impact by imposing
additional water quality protection measures as necessary.
Other minor activities by others in District facilities are taken intoaccount by the District in its permit review process. Refer to Chapter II.E.4.
Definition of Potential for Cumulative Impact for a list of current major stream
projects by others and a summary of the general amount of such projects
reviewed by the District each year. The District comments on new projects
proposed by other agencies or property owners within 50 feet of a creek to
determine if they will affect the flow of water, collect debris, or will adversely
affect the ability of channel banks to carry flood waters or resist erosion
(District Ordinance 83-2). The District encourages projects to be designed so
as to avoid unstable bank conditions, large increases in discharge, or conditions
that might cause pollution. Additionally, the District and the various cities
participate in a Non-Point Source Control Program as defined in Section III of
this document. One of the main purposes of District review of channel
encroachment and construction by others in and near channels is to prevent
incorrectly designed or poorly installed work from causing channel
sedimentation or bank failure. These stream projects by others are not expected
to cumulatively result in additional impacts along with the SMP for two
reasons. First, by reviewing these other projects under its permit program, the
District is usually able to avoid any significant effects to the streams. Second,
SMP activities are proportionally much greater in size (265 miles of streams)
than stream projects implemented by others, yet the SMP avoids or mitigates
for most of its own impacts, thus there is no cumulative effect when combined
with these much smaller projects.
|