|
RETURN
TO TABLE OF CONTENTS
LAND USE AND COMMUNITY VALUES
This section discusses environmental issues that define a livable community: land use planning,
aesthetics, air quality, noise, public services and recreation. The District's Stream Maintenance
Program will not directly cause any substantial change in land use or be incompatible with surrounding land
uses throughout Santa Clara County because maintenance will be confined to District property or easement.
Land uses on adjacent parcels may be indirectly affected by changes in visual condition, dust, odor, noise,
or changes in access created by maintenance work. These potential impacts on community values are
reduced to less than significant by either the short-term period over which these conditions occur at any one
location, or by application of best management practices
Much of the routine maintenance will take place in built-up areas within cities, as opposed to rural
county areas. The potential significance of land use and community value impacts is related to the type of
land uses adjacent to creeks and canals as well as the frequency and duration of the impact. In general, since
the District's maintenance work is either directly requested by the landowners or occupants adjacent to the
creeks, or is done for their benefit, the landowners would not be overly sensitive to such effects if they occur.
The adjoining land use sensitivity is also reduced because the duration of the work is relatively short (a few
days or weeks), and infrequent (once a year or less often).
1. Land Use and Planning
a. Setting
1) Geography of Santa Clara County Streams
During the early 1900's, farmers straightened and sometimes relocated
many creeks in Santa Clara County. These stream changes were intended to
facilitate agriculture and were not designed to carry major flood flows. Since
1929, the predecessors to the present-day Santa Clara Valley Water District
further modified creeks by excavating channels, building levees and providing
drop structures at large grade breaks. As the years went by, a higher level of
flood protection was needed, and many creeks were channelized to a
trapezoidal configuration and lined with concrete.
The pattern of development and urbanization in the Santa Clara Valley
over the past 50 years is characteristic of post-World War II development
throughout suburban California. Houses, apartments, commercial and industrial
facilities, roads, freeways and parking lots have been created in areas once
covered with orchards and fields. Infrastructure such as sewers and storm
drains have been buried underground, with outfalls to streams or to the bay.
Most importantly, streams that were at the top of the alluvial fan were
impounded by reservoirs, then further narrowed and channelized which allowed
development on the historic floodplains.
Today, the land uses adjacent to the watercourses include a full range of
uses (e.g. residential, commercial, industrial, public, open space) under the land
use jurisdiction of either Santa Clara County or one of its 15 incorporated cities.
Each jurisdiction currently has as its goals the preservation of open space and
the riparian corridors, but historically, most prior development has not
considered the natural character of streams as an amenity. Houses are located
adjacent to a narrowed riparian corridor, with back-yard fences at the tops of
banks.
2) Maintenance Program and Local Land Use Jurisdictions
The District is a special district with its own charter, and manages its
mostly linear properties within the jurisdiction of the cities and County for the
primary purposes of flood protection and water supply. The District does not
have any authority to control land uses under the jurisdiction of the cities and
County. However, land uses on adjacent properties, no matter the jurisdiction,
can affect each other, therefore, a general description of the types of land uses
adjacent to creeks and canals is provided below. For more information
regarding jurisdictional issues, please see Chapter III, Plans, Ordinances and
Policies.
The greatest extent of creek lengths in SCVWD jurisdiction are in the
County, the City of Gilroy sphere of influence, and the City of San Jose and its
sphere of influence.
Most of the proposed sediment removal, vegetation management, and bank
protection work is expected to take place within incorporated cities. For certain
creeks (e.g. Canoas, Madrone Channel , Sunnyvale East Channel), all of the
creek within each respective jurisdiction will be impacted by sediment removal
under the proposed program.
3) Land Uses Adjacent to Creeks
In the SCVWD jurisdiction, 25% of the creeks run through residential
areas (low to high density), 50% through natural open space or agriculture, 5%
through recreational and park land, and the remaining 20% is variously
commercial, institutional or industrial (TRA, 1997). Creeks with large extent
of residential land use (more than 3 miles) adjacent to channels include Adobe,
Matadero, Permanente, San Francisquito and Stevens, San Tomas Aquino,
Saratoga, Wildcat Creeks and Sunnyvale East Channel, Canoas, Los Gatos,
Ross Creeks and the Guadalupe River, and Lower Silver Creek. Creeks through
residential areas have a greater potential for land use issues because of the
higher numbers of affected citizens.
The greatest extent and proportion of natural open space and agricultural
lands adjacent to creeks is in the Pajaro River Basin (101 miles), compared with
71 miles in the Santa Clara Basin. Open space, agricultural and park uses tend
to have fewer land use issues because there are relatively fewer users and less
potential for property damage due to flooding.
b. Significance Criteria
A project would be normally considered to have a significant effect on
land uses if one or more of the following factors were met:
Criterion LU-1 Conflict with any applicable land use plan, policy or
regulation of the jurisdiction in which the project is located
adopted for the purpose of avoiding or mitigating an
environmental effect.
Criterion LU-2 Physically divide an established community; for example,
installation of an above-ground pipeline through an
established neighborhood that would cause a permanent
disruption in the physical arrangement of that
neighborhood.
c. Impacts
1) Overview
The land use discussion below is in accordance with the significance
criteria outlined above. If the maintenance projects conform to the BMPs
included in the proposed program, there will be no significant land use impacts.
These BMPs are described in the Project Description section of this EIR and the
relevant BMPs are summarized at the end of each of the following subsections.
Many land use impacts are annoyance impacts such as increase in noise,
dust production, and odor or decrease in aesthetic qualities, as well as
interference with access. All of these effects are described in their respective
sections in this chapter. The potential significance of impacts is related to the
type of land uses adjacent to creeks as well as the frequency and duration of the
impact. In general, since the District's maintenance work is either directly
requested by the landowners or occupants adjacent to the creeks, or is done for
their benefit, the landowners are by and large not sensitive to such effects, if
they occur.
The adjoining land use sensitivity is also reduced because the duration
of the work is relatively short (a few days or weeks), and infrequent (every
other year or less). Historic records from 1977 to 1999 indicate that the average
duration of sediment removal work is 10 working days, with an average of
3,200 cy of material removed. The duration of sediment removal work is very
project specific, however, and duration has ranged from ½ day (6 cy) to 84 days
(7,040 cy along San Tomas Creek in 1992). Historic records for erosion repair
work indicate that the average duration of a bank stabilization project is 10
working days. Duration has ranged from 1 day (repairing 1,900 lineal feet of
gabion baskets) to 104 days (installing 520 feet of sacked concrete along
Saratoga Creek in 1990)(Mary Stone, personal communication, 2/15/01). By
comparison, the duration of most vegetation management activities in an area
is usually a few hours. However, for hand removal of vegetation from a
channel, the work can take place in the same neighborhood from ½ day to 5
working days. During that time period, the work will progressively move along
the stream and won't be located behind any single home for longer than a few
hours (Mark Wander, personal communication, 2/01/01).
2) Sediment Removal, Vegetation Management and Bank
Protection Activities
The District's Maintenance program will not directly conflict with any
applicable land use or be incompatible with surrounding land uses. The
requirement for the District's work is related to the prior land use change which
has contributed to the need to modify and provide flood protection of the
creeks. The program is a result of prior land use change; the program does not
cause land use change. As there are no proposed land use changes, there is no
impact.
The District's Maintenance program will not alter or be in
nonconformance with any regional, federal, state land use or environmental
plans or policies (see Chapter III, Plans, Ordinances and Policies). The land
uses within the District will not change as a result of the proposed program.
There is no impact.
The District's Maintenance program will not conflict with the County's
flood protection management policies of the 15 cities and County government.
This is also further discussed in Chapter III. One of the main objectives of the
Stream Maintenance activities is to increase flood protection by restoring flood
capacity (where possible, to the 1% level for sediment removal and 2% for bank
protection). The effects of maintenance on the risk of substantial flooding may
result in a beneficial impact.
The District's maintenance program will not disrupt the physical
arrangement of any community. No above-ground pipelines will be installed
as part of the proposed project.
2. Aesthetics
a. Existing Conditions
The streamside areas within the District vary widely and hence the
sensitivity to aesthetic or visual impact varies widely. Open space along the
District's creeks is found mostly in the agricultural and semi-rural areas in the
south county. Riparian remnants occur in the north county areas in the less
urbanized and foothill areas. In the heavily urbanized areas, development along
streams have been often designed without visual contact or physical interaction
with the channel, except at road crossings, where the creek is enclosed in box
culverts. Many of the streams are closed off by chain link fences at the bridge
crossings.
The chapter on Geomorphology (IV. A.) defined five types of channels
that characterize the work area of most of the District's maintenance effort.
These physical classifications tend to share a similar visual setting and are a
convenient way to organize a discussion of the project's potential aesthetic
effects. A discussion of five types of channels in the District and the existing
viewsheds in these types follows.
Most of the urban area of the Santa Clara Valley is built on alluvial fans,
foothill valleys and alluvial flood plains. Thus, many of the channels in the
Type 1 streams (Alluvial Fans, Foothill Valleys and Alluvial Flood Plains) are
encroached by residential, commercial and industrial uses right up to the tops
of channel banks. These channels vary in vegetation types and quantities, from
bare ground and sack concrete to heavily wooded willow thickets. Because of
the flood plain and bank encroachment, middle and long-distance view
corridors are not usually present. In agricultural areas of the South County,
vegetation, especially willow thickets, are the main indicator of a stream in the
area. The extent of vegetation in these channels depends upon the area of
flood plain. Recreational trails along many of the streams are currently being
implemented (San Tomas Aquino Creek, Guadalupe River, Coyote Creek), with
more trails in planning stages.
Types 2 and 3 streams (Deltas and Tidal Channels) are wider, straighter
and flatter, offering more middle and long-distance views. However, views of
the channel from other areas and views from inside the channel may be
constrained by tall levees . These channels also vary widely in vegetation types
and quantities, but most Types 2 and 3 streams contain bands of wetland
vegetation (tules, willows) along the edges of the channel.
Types 4 and 5 streams (Channelized Streams and Streams Influenced by
Hydraulic Structures) can be wide compared to unmodified channels. These
channelized streams are flood protection channels designed to maximize flow
area and minimize hydraulic roughness. Slopes are usually unvegetated
concrete or rock. Hydraulic structures such as bridges, culvert crossings, bank
protection structures, concrete channel sections and other structures are present
in channelized streams and are highly visible.
b. Significance Criteria
A project would normally be considered to have a significant effect on
aesthetics if one or more of the following factors were met (CEQA Guidelines:
Criterion Aes-1 Permanently and substantially alter or degrade the visual
character or quality of the site and/or surrounding area due
to:
-- Major natural landform alteration, e.g. one or more
distinct and prominent geologic or topographic
features would be destroyed, permanently covered or
substantially modified. Such features may include,
but are not limited to, hilltops, ridges, canyons,
ravines, and rock outcrops.
-- Removal of major stands of vegetation and/or trees
which are a visually prominent feature of the
landscape as seen from public areas.
-- Removal of visually prominent rock outcroppings, or
-- Introduction of structures that are not of the same
style or scale as surrounding development.
-- Result in permanent structural development located
within ½ mile of a designated scenic highway that
would be highly visible in a way that detracts from
the existing scenic quality and character of the
corridor.
Criterion Aes-2 Permanently and substantially obstruct or block any scenic
vista or view corridor that is designated on local plans as a
significant or important view corridor or scenic area.
Criterion Aes-3 Produce a new source of substantial light and glare, which
would adversely affect day or nighttime views in the area
or pose a nuisance. This includes ambient nighttime
illumination levels that would be increased beyond the
property line or use of highly reflective building materials.
c. Impacts
1) Overview
The potential for aesthetic impact is limited because, in most cases,
channelized creeks in urban residential and commercial areas of the District are
screened from view except from immediately adjacent land parcels. The
channel bottoms where maintenance is done are below grade and not always
visible from adjacent land uses.
Residents adjacent to creeks or creek-side trail users could be temporarily
affected by stream maintenance activities. If maintenance projects conform to
the BMPs included in the proposed program, there will be no significant
temporary or permanent aesthetic impacts to sensitive receptors. These BMPs
are described in the Project Description section of this EIR and are also listed
at the end of each of the following subsections of Sediment Removal,
Vegetation Management and Bank Protection.
Maintenance has a beneficial effect on aesthetics when work crews
remove trash and debris in and along creeks.
No local, state or federally-designated historic buildings will be affected
by the SMP. Nor will it have any adverse effects on any areas within a
designated state scenic highway corridor would be altered. No scenic vistas or
view corridors that are designated on local plans would be permanently or
substantially altered.
Stream Maintenance activities normally occur only during daylight
hours, from 7:00 a.m. to 5:00 p.m. Night lighting is rarely used and thus
maintenance activities would not produce a new source of substantial light and
glare.
2) Sediment Removal
Removal of sediment may also remove vegetation from the channel.
Depending on the aspect from the surrounding land uses, this may result in a
scenic vista being temporarily changed from that of a vegetated creek to a
partially vegetated or bare creek until the vegetation regrows. Large trees are
not removed by these types of routine stream maintenance activities and the
bottom of the channel is not always visible from adjacent land uses.
Sediment removal sites would not be altered permanently by sediment
removal activities as many of these activities are cyclical (sediment is removed
during the dry season, then more sediment is deposited at the same reach during
the following rainy season). While large equipment in creek channels, creek
banks and along levees would be visible to sensitive receptors, sediment
removal activities are temporary. There will be no significant temporary or
permanent aesthetic impacts to sensitive receptors from sediment removal
projects. However, there still may be negative environmental effects resulting
from sediment removal activities that are below the stated thresholds of
significance. Implementation of the following BMPs will reduce these negative
environmental effects:
| 1.4 |
Avoid Erosion When Restoring Flows |
| 1.6 |
Use of Wheel and Track Mounted Vehicles in Stream Bottoms |
| 2.1 |
Minimize Vegetation Removal |
| 2.2 |
Minimize Stream Access Impacts |
| 3.6 |
Remove Sediment from One Side of Large Channels in Alternate
Years |
| 4.3 |
Stabilized Construction Entrance |
| 4.6 |
Work Site Solid Waste Management |
3) Vegetation Management
Vegetation management could permanently alter and degrade the visual
character of creeks if it were to remove major stands of large vegetation, such
as willow thickets along the Pajaro River. However, large stands of trees would
not be removed by routine vegetation management activities, as the District's
policy is to not remove material in creeks larger than 6" diameter at breast
height (dbh) by mechanical means, or larger than 2" dbh by herbicides. This
effect is considered Less than Significant, as there will be no permanent change
in these willow-covered creek channels from vegetation removal activities.
Depending upon the aspect from the surrounding land uses, vegetation
management activities may cause a scenic vista to be temporarily changed from
that of a vegetated creek to a partially vegetated, or bare creek until vegetation
regrows.
Vegetation removal on levees and maintenance roads will be limited to that
necessary for facility inspection purposes, to meet regulatory requirements, to
comply with fire codes, provide visual clearance to inspect the condition of a
facility, and to meet capacity requirements. If maintenance work leaves slopes
in a bare soil condition, the District will plant slopes with native vegetation or
use other soil stabilization techniques consistent with the facility's design and
the probable success of revegetation. There will be no significant temporary or
permanent aesthetic impacts to sensitive receptors from vegetation management
projects. However, there still may be negative environmental effects resulting
from sediment removal activities that are below the stated thresholds of
significance. Implementation of the following BMPs will reduce these negative
environmental effects:
| 2.2 |
Minimize Stream Access Impacts |
| 2.5 |
Planting |
| 2.6 |
Mulching |
| 2.9 |
Revegetation Site Maintenance |
| 6.1 |
Spill Prevention |
4) Bank Protection
Bank protection may either replace an eroded earthen bank with soft
structures (vegetated slopes, willow wattles), hard structures (i.e., rock,
concrete, sack concrete), or a mix of soft and hard structures. The District
estimates that approximately 1 mile of bank protection work would be done
annually. Thus, bank protection work could occur on 20 miles of the
approximately 1650 miles of bank under District jurisdiction over the life of the
program. Bank protection rarely results in the removal of large trees, because
the eroded bank is usually unvegetated by the time an erosion problem has
developed.
Bank protection activities could have significant and cumulative visual
impacts to sensitive receptors such as trail users, homeowners and adjacent land
users (in areas of high visibility) if BMPs were not implemented.
Implementation of the following BMPs will reduce potential impacts to a less
than significant levels:
| 1.11 |
Concrete use near waterways |
| 2.2 |
Minimize Stream Access Impacts |
| 2.3 |
Minimize Hardscape in Bank Protection Design |
| 2.5 |
Planting |
| 2.6 |
Mulching |
| 2.9 |
Revegetation Site Maintenance |
| 3.14 |
Maintain or Provide Escape Cover |
3.Air Quality
a. Setting
The Stream Maintenance program is located in Santa Clara County which
lies along the southern portion of the San Francisco Bay. The climate of the
San Francisco Bay region is classified as Mediterranean, with little or no
precipitation during the summer months and moderate precipitation during the
winter months. This climate is controlled primarily by the Pacific High which
migrates northward during the summer months holding storm tracks well to the
north. During the winter months, the Pacific High migrates southward
permitting storm centers to swing into and across California. Rainfall is
variable across the project area, generally higher on the west and at higher
elevations. The seasonal climate dictates that maintenance work is usually done
in the drier summer and fall period.
All of Santa Clara County is in the Bay Area Air Quality Management
District (BAAQMD). The Bay Area is in attainment for all national ambient
air pollutant standards, but is in non-attainment for state standards for two
pollutants, ozone (one-hour standard) and fine particulate matter (PM10, both
annual mean and 24 hour standards). Fine particulate matter represents the
respirable fraction of particulate matter and is termed PM10 for particles
smaller than 10 microns in diameter (regulated by the state) or PM2.5 for
particles smaller than 10 microns in diameter (regulated by the state). Mobile
sources - vehicles - are major sources of these pollutants, with wood fires and
unpaved roads contributing also to PM10. Generally, combustion tends to
produce the finer particles and mineral earth sources of dust, such as
earthmoving, tend to produce coarser particles.
b. Significance Criteria
A project would be normally considered to have a significant effect on air
quality if one or more of the following factors were met (CEQA Guidelines):
Criterion AQ-1 Violate any air quality standard or contribute to an existing or
project air quality violation.
Criterion AQ-2 Major alteration of air movement, moisture or temperature, or
any change in climate, either locally or regionally.
Criterion AQ-3 For a stationary use or permanent project operations, result in
a generation of emissions of or in excess of 80 pounds per day
for ROG, NOx, or PM10 or 550 pounds per day of carbon
monoxide.
Criterion AQ-4 Result in temporary generation of dust (PM10) due to sediment
removal in stream or drainage channels equivalent to grading
an area of 2.2 acres per day.
Criterion AQ-5 Expose sensitive receptors (i.e., residents, schools, hospitals)
to substantial pollutant concentrations, i.e. those that exceed
the BAAQMD standards identified above.
Criterion AQ-6 Emit toxic or hazardous air pollutants resulting in a significant
increased human health risk, in which the probability of
contracting cancer for the Maximally Exposed Individual
(MEI) exceeds 10 in one million or ground-level
concentrations of non-carcinogenic toxic air contaminants
would result in a Hazard Index greater than 1 for the MEI.
Criterion AQ-7 Create frequent objectionable odors affecting a substantial
number of people (500 or more) or create other nuisance
problems.
Criterion AQ-8 Conflict with or obstruct implementation of Bay Area Air
Quality Management Plan.
For construction activities, BAAQMD significance criteria emphasize
implementation of effective and comprehensive dust control measures. The
BAAQMD considers any construction project that complies with the
appropriate dust control measures to be less than significant.
c. Impacts
1) Overview
These maintenance activities are essentially construction activities and have
a similar potential for air pollutant emissions: diesel exhaust emissions from
equipment at the work site (including mowing), spray rigs and on-highway
trucks, and fugitive particulate (dust) from disturbed earth at the work site and
from hauling sediment and green waste to upland locations. If the maintenance
projects conform to the BMPs listed as part of the proposed program (including
BAAQMD dust control measures), there will be no significant PM10 impacts
to sensitive receptors.
2) Criteria Pollutants
Air quality can be affected by both fugitive and exhaust emissions.
Fugitive PM10 emissions are the most potentially significant. Emissions from
maintenance vehicles would be short term and spread out over the length of
channel. Because these activities are temporary construction projects, the
potential for localized high concentrations of air pollutants is low.
Residences, recreational trails, commercial/office uses and agricultural uses
are all considered sensitive receptors and are often located near creeks. PM10
emissions would not be significant, because these activities would be
temporary. Sensitive receptors would occasionally be exposed to large
particulate (visible dust) from construction. Dust exposure potential for any
one receptor would decrease as activity moved downstream and would end once
the short term project is completed.
If the maintenance projects conform to the BMPs included in the proposed
program, there will be no significant permanent air quality impacts. These
BMPs are described in the Project Description section of this EIR and are also
listed at the end of each of the following subsections of Sediment Removal,
Vegetation Management and Bank Protection.
3) Sediment Removal
Annual sediment removal work entails handling large volumes of earth and
off-site disposal. The annual average of roughly 80,000 cubic yards of
sediment on about 16 miles of channel may vary from year to year, depending
in part on rainfall conditions of the past season. Trucks traveling over dirt
roads, gradealls, trucks hauling sediment, and other maintenance activities will
lift particulate matter and suspend it in the atmosphere. The potential for
fugitive dust is reduced because most creek work areas are naturally damp and
because most of the drier, non-tidal sites have a coarse particle size with a low
silt content. Local emissions are caused largely by travel on unpaved roads and
earth spilled onto paved roads.
The average sediment removal construction period is 10 working days,
though this activity can last as long as 3 months. Sediment removal sites
typically have an area of less than 4 acres, and only about 10% of this area is
worked on in any one day: work teams proceed from one end of the site to the
other at a rate of 200 to 400 feet per day. Teams move from site to site through
the course of the summer to carry out maintenance activities where they are
needed. While individual work sites may be of short duration and small area,
cumulatively, the District's work will affect several tens of acres spread over
a roughly six-month activity period. In order to minimize the cumulative
effects of maintenance on dust and PM10 generation, standard BAAQMD
controls are adopted as BMPs.
If the maintenance projects conform to the BMPs listed as part of the
proposed program (including BAAQMD dust control measures), there will be
no significant PM10 impacts to sensitive receptors.
| 4.3 |
Stabilized Construction Entrance |
| 5.1 |
BAAQMD Basic Dust Control Measures |
| 5.2 |
BAAQMD Enhanced Dust Control Measures |
4) Vegetation Management
Vegetation management activities typically involve using vehicles to travel
to the job sites and using mowers and spray rigs once at the job sites. As listed
above , these activities from maintenance vehicles would be short term and
spread out over the length of channel. Because these activities are temporary
construction projects, the potential for localized high concentrations of air
pollutants from engine exhaust is low.
Vegetation management projects can cause PM10 effects as dust is raised
from mowing and traveling along dirt roads during the dry season. The
implementation of the BAAQMD dust control measures will reduce air quality
effects from vegetation management activities to less than significant levels.
Herbicide application uses water as a carrier and the potential for volatile
organic gas emissions is minimal. The herbicides used for vegetation
management are not hazardous air contaminants when used in accordance with
state law. The broader issue of pesticides and public and environmental health
is addressed in Chapter IV. F., Public Health and Safety. If the maintenance
projects conform to the BMPs listed as part of the proposed program (including
BAAQMD dust control measures), there will be no significant PM10 impacts
to sensitive receptors.
| 4.3 |
Stabilized Construction Entrance |
| 5.1 |
BAAQMD Basic Dust Control Measures |
| 5.2 |
BAAQMD Enhanced Dust Control Measures |
Bank Protection
Bank protection work typically averages 8 days. In addition to the vehicles
used to travel to the job sites, equipment used for bank protection may include
excavators, dozers, cranes, loaders and 10-and 20- cubic-yard dump trucks,
concrete trucks, and pumps and water trucks. Water pumps and piping, and
cofferdams of earth, gravel, sandbag, hay bales or rubber or other suitable
material may be brought by large vehicles to the work sites. As stated above,
emissions from maintenance vehicles and fugitive dust from operation of these
vehicles would be short term and spread out over the length of channel. The
following BMPs will reduce or avoid all impacts from fugitive dust and air
emissions.
| 4.3 |
Stabilized Construction Entrance |
| 5.2 |
BAAQMD Enhanced Dust Control Measures |
Cumulative Emissions
Cumulative emissions for all Stream Maintenance activities for the District
are shown in Table IV-C-1. Note that these emissions would be generated at
several locations distributed over the entire District and that they would occur
for short periods at each location. Emissions for a typical site that also includes
dust control measures are presented in Table IV-C-2.
Table IV-C-1
District-wide Maintenance Emissions (Pounds)
|
Average Day 1 |
Maximum Day2 |
Annual Total |
| Pollutant3 |
Equipment
Emissions |
Fugitive
Emissions |
Equipment
Emissions |
Fugitive
Emissions |
Equipment
Emissions |
Fugitive
Emissions |
| PM10 |
11 |
34 |
21 |
69 |
740 |
241 |
| CO |
676 |
-- |
1,350 |
-- |
47,300 |
-- |
| ROG |
45 |
-- |
90 |
-- |
3,150 |
-- |
| NOx |
208 |
-- |
415 |
-- |
14,500 |
-- |
| SOx |
23 |
-- |
45 |
-- |
1,570 |
-- |
Source: Thomas Reid Associates and the BAAQMD CEQA Guidelines,
Assessing the Air Quality Impacts of Projects and Plans, April 1996.
All calculations based on 42,000 gallons of diesel fuel used per year, a 70
day work year, an average site size of 3.37 acres, and 10% of each site is
worked on in the maximum day.
1 Assumes 2 teams working simultaneously in 2 different parts of the District.
2 Assumes 4 teams working simultaneously in 4 different parts of the District.
3 PM10 -- Fine particulate matter, less than ten microns in diameter, respirable.
CO -- Carbon monoxide
N0x -- Nitrogen oxides
ROG -- Reactive organic gases
S0x -- Sulfur oxides
Table IV-C-2
Emissions for a Typical Site with Basic Dust Control Measures
(Pounds/Day)
| Pollutant1 |
Equipment
Emissions |
Fugitive
Emissions |
Total |
| PM10 |
5.3 |
8.6 |
13.9 |
| CO |
338.5 |
-- |
338.5 |
| ROG |
22.5 |
-- |
22.5 |
| NOx |
103.8 |
-- |
103.8 |
| SOx |
11.3 |
- |
11.3 |
5) Odor
Sediment Removal
The sediments removed from channels have some potential to release odor
or to build up odorous gases when stockpiled. The problem has been
encountered in the past and is particularly associated with sediments in tidal
areas that have high organic material and saltwater content. Under anaerobic
conditions, microorganism metabolism of organic material often produces
malodorous, volatile organic compounds. Seawater contains sulfate ions, which
microorganisms can use in the metabolic process, producing reduced sulfur
compounds, hence the rotten-egg smell of some tidal mudflats.
These conditions are unavoidable in tidal areas. The potential for odor
comes from the initial removal process, and from sediment stockpiling to
dewater or schedule removal. In the stockpiles, fine-grained sediment will
impede air movement and lead to anaerobic conditions. When there are large
volumes of organic material present, as from stockpiles with heavy wetland
vegetation, the stockpile will release odors. In general, when the pile is
disturbed again for removal, odor will be released at the site and from the trucks
carrying the material off-site.
The extent of odor is difficult to predict. Low wind speed and/or winds
directing odor at residential areas would obviously exacerbate the problem.
Favorable conditions for initial sediment work and subsequent removal would
be sunny and windy days (because unstable atmospheric conditions favor rapid
dispersal). These conditions are common in summer and early fall. This
corresponds to the July 1 through October 15 period of Stream Maintenance.
Stockpiles left beyond the end of the normal maintenance period into winter
when unfavorable meteorological conditions are more likely to have a greater
potential for causing odor problems. If the maintenance projects conform to the
BMPs listed below there will be no significant odor impacts to sensitive
receptors.
| 5.3 |
Avoid Stockpiling Potentially Odorous Sediments |
Vegetation Management
Dead vegetation has minimal potential for odor when left in place because
the mass of material is small and there is adequate air for gradual aerobic
decomposition. Where vegetation is removed and piled along a channel, there
may be odors unless the piles are adequately aerated. This problem is similar
to any debris management for landscaping or agriculture. Green waste is
typically disposed of at green waste landfills or on District property where the
waste is composted. Herbicide residue does not affect disposal. Therefore,
there is no impact.
Bank Protection
Bank protection has little potential for odor, because it does not require the
removal or stockpiling of large amounts of sediment or vegetation subject to
potential odorous conditions. Therefore, there is no impact.
4. Noise
a. Terminology
Noise is unwanted sound. Noise is measured on the logarithmic decibel
scale (dB), usually with a frequency sensitivity that matches the human ear,
called "A-weighting." Thus, most environmental measurements are reported
in dBA, decibels on the A-scale. Because decibels are logarithmic units, the
noise level in dBA from two noise sources are not arithmetically additive. For
example, doubling of the noise energy by the addition of two equal noise
sources results in an increase of 3 dB (e.g. 56 dBA + 56 dBA = 59 dBA).
The equivalent noise level, Leq, represents the level of a steady noise
having the same sound energy as the time-varying noise measured. Leq(x)
represents the time-weighted average for x minutes, while Leq(h) is used to
describe the time-weighted average for one hour. Leq will be used to describe
the noise levels produced by District activities.
According to State general plan law, cities and counties must describe the
noise characteristics of areas within their jurisdictions using measures that
account for both the daytime and nighttime noise levels. Twenty-four hour
noise environment exposure over a day is often described by CNEL
(Community Noise Environment Level) or DNL (day/night level),
measurements that assign penalties to noise levels that occur in the quieter
evening and nighttime hours, to account for the increased annoyance and
intrusive quality of nighttime noise. CNEL will be used to describe the overall
noise environment of areas within the scope of the proposed program.
Noise spreads out uniformly in waves from a source and attenuates
(decreases in force and magnitude as it spreads) at a rate of 6 dB decrease in
noise level for distance doubled. Sensitive receptors are persons and facilities
that could be adversely affected by noise. To predict the noise impacts of the
program on sensitive receptors, noise levels must be determined away from the
site at the location of sensitive receptors. Treating the project equipment as a
"point" or stationary noise source, the noise levels can be predicted at any
distance because sound pressure varies inversely away from a source. By
theory, noise attenuation from a point source is 6 dB for each doubling of the
distance from the source. In practice, "soft" non-reflective ground and
intervening vegetation between the noise source and the receptor produce a
drop-off of 9 dB for each doubling of distance and air absorption over distances
greater than 1,000 feet increases noise attenuation.
b. Noise Policies
Each of the cities and Santa Clara County have policies and guidelines for
their jurisdictions that attempt to minimize the effects of noise on people
through construction standards, zoning restrictions, hours of operation and
suppression techniques. Goals for noise levels are defined that are compatible
with the various land use types within each jurisdiction. However, all
jurisdictions recognize that higher than standard noise levels will be generated
from time to time by heavy equipment engaged in construction or maintenance
activities throughout the jurisdiction. Because heavy-equipment noise is an
unavoidable necessity to modern life, jurisdictions typically include wording
in noise ordinances and elements exempting these short-term, temporary, higher
noise levels from compliance with the overall standards for the various land
uses.
c. Setting
Within the district boundaries, background noise levels vary greatly from
the very low noise levels in the semi-rural western and eastern foothills to the
high noise levels of the urbanized central Santa Clara Valley floor. The highest
noise levels in the project area would probably be encountered in the vicinity
of the San Jose International Airport. The noise environment of the north
central portion of the Santa Clara Valley is heavily influenced by takeoffs and
landings and, in accordance with State law, the airport monitors noise levels
throughout the Valley to identify the area most impacted. Noise monitoring has
defined an elliptical contour around the San Jose Airport within which noise
levels from aircraft alone exceed 65 dBA CNEL. More localized noise sources
such as traffic on nearby freeways and surface streets would further elevate
CNEL within this area.
Noise generated by heavy equipment engaged in Stream Maintenance
activities could impact sensitive land uses adjacent to the proposed sites for
future work. Land uses sensitive to noise generation are primarily those with
an outdoor use component that includes an expectation of quiet noise levels.
Low noise levels can normally be accomplished for interior spaces through
modern construction techniques. Interior noise levels inside residences
adjacent to creeks would typically be less than 45 dBA CNEL with the
windows closed because of the noise attenuation provided by walls and
windows. Examples of sensitive land uses include backyards and gardens in
residential areas, parks and open space reserves, outdoor shopping areas,
schoolyards and cemeteries. In these areas, excessive noise levels would be a
nuisance to outdoor users. Typically, outdoor areas cannot be easily shielded
from high noise levels without the construction of intervening barriers.
d. Significance Criteria
A project would be normally considered to have a significant effect on
sensitive receptors if one or more of the following noise factors were met:
Criterion N-1 Expose persons to or generate permanent noise levels in excess
of standards established in the local general plan, noise
ordinance or applicable standards.
Criterion N-2 Result in a substantial permanent increase/change in the
ambient noise level (i.e. a 5 dBA increase in an area where the
existing noise level is considered acceptable or a 3 dBA
increase in areas where existing noise levels are not considered
acceptable, as defined by state or local noise/land use
compatibility standards) or generate noise levels in excess of
65 dBA CNEL at the property line that could affect residents,
schools or hospitals (The sources for these levels are the
General Plans of the County and each city).
Criterion N-3 Create substantial and prolonged increased noise levels over
the course of the construction period, especially in residential
areas during evening, weekend and nighttime hours or anytime
within 1,000 feet of sensitive receptors (i.e., schools,
hospitals).
Criterion N-4 Expose persons to or generate excessive, continuous ground
borne vibration.
e. Impacts
1) Overview
Stream Maintenance practices typically involve the use of heavy machinery
and equipment. This equipment may include bulldozers and other earthmovers,
dump trucks, gradalls and other wheeled vehicles. Vegetation management can
be accomplished through mowing, discing, hand clearing or herbicide
applications (depending on the environmental conditions of the site). Mowing
and discing can be accomplished through either large tractors or mowers. The
muffling of this equipment is part of the standard District practices in areas
where residences, businesses or other sensitive receptors would be affected. If
the project conforms to the BMPs included in the proposed program, there will
be no significant permanent noise impacts to sensitive receptors. These BMPs
are described in the Project Description section of this EIR and are also listed
at the end of each of the following subsections of Sediment Removal,
Vegetation Management and Bank Protection.
Many of the creeks have an overall width of less than 100 feet. For heavy
equipment to operate in these creeks, it is necessary to either position this
equipment immediately adjacent to property lines on the top of the bank (and
in many cases, adjacent to backyards) or directly in the creeks.
Noise impacts from heavy equipment are limited to the hours of the week
typical of other construction and maintenance activities. Stream Maintenance
is generally scheduled for Monday through Friday. Field crews report to the
maintenance yard at 7:00 am and arrive at work sites between 7:30 am and 8:00
am depending on the distance from the maintenance yard to the work site. Field
work stops at approximately 3:30 pm and crews return to the maintenance yard.
In a typical work day, equipment could be operating as long as 7 hours (Dennis
Ely, pers. comm., 1996).
Because maintenance is a transient activity, no permanent change results
and the significance thresholds addressing permanent noise sources do not
apply. Construction type impacts are judged non-significant if they are limited
to the conventional work day. In the following discussion, the potential for
noise impacts is determined to be insignificant according to the District criteria.
Because maintenance will produce activity in what is usually a quiet area,
maintenance noise may be perceived by neighbors as disturbing or intrusive to
privacy. Some of that intrusion could be minimized by advance notice so that
neighbors are not surprised by unaccustomed noise.
Routine stream maintenance may occur in the vicinity of local airports,
such as along the Guadalupe River adjacent to San Jose International Airport,
and along streams near Reid-Hillview and San Martin Airports. Temporary
noise levels may exceed 75 dBA, however, data in the CalTrans' Division of
New Technology, Materials and Research Technical Analysis Notes states that
jet flyovers at 1,000 feet in elevation can produce 110 dBA. Because stream
maintenance is short-term and substantially quieter than jet flyovers (73 dBA
vs. 110 dBA), no permanent significant impacts would occur.
2) Sediment Removal
Occasionally, it may be necessary to work outside of the normal 7:30 am
to 3:30 pm time period, or work on weekends to meet special site conditions,
respond to pending bad weather, or complete work before the end of the season.
Except under special circumstances, it is the goal of the District maintenance
staff to conform to the hours of construction activity for the jurisdiction in
which the work is being performed. For example, when working within the
City of Campbell, field crews do not begin before 8:00 am in keeping with that
City's regulations (Dennis Ely, pers. comm., 1996).
To remove sediment from creek channels or place riprap on channel slopes,
heavy equipment operates from either the top of the bank, if accessible, or
within the channel itself. When working within the channel, the channel slopes
would serve to shield receptors from noise generated by heavy equipment.
Receptors adjacent to District facilities would be less shielded from heavy
equipment operating on the top of the bank.
Monitoring of a district excavator sited on the top of the bank and removing
sediment from Lower Penitencia Creek channel recorded an Leq of
approximately 67 dBA at 100 feet (TRA, 1995). Given standard attenuation of
9 dB per distance doubled for soft noise, an excavator working 50 feet from a
residential backyard with soft ground and intervening vegetation would
generate 76 dBA. Sediment removal projects typically progress at a rate of 200
to 400 feet of creek channel per day (Dennis Ely, pers. comm., 1996). A typical
subdivision lot at 60 feet wide and 50 feet from operating equipment would be
subject to 73 dBA for one to two hours during sediment removal operations.
As the equipment moves further along the channel, noise levels would attenuate
until equivalent to the background noise levels and would no longer be
perceptible.
Because these activities are temporary, they are not considered significant.
The following BMPs will provide notice and reduce intrusiveness to neighbors.
BMPs which reduce or avoid all significant Noise impacts from Sediment
Removal projects:
| 4.1 |
Notify Local Governments of Scheduled Work |
| 4.2 |
Minimize Disturbances to Surrounding Neighborhoods |
3) Vegetation Management
Of the three basic Vegetation Management methods, hand removal (which
includes chain saws, weed eaters, etc) and mechanical (including mowing and
discing) have the highest potential to create high noise levels. Hand removal
with chain saws produces noise levels of 75 dBA at 100 feet, but chain saws are
used infrequently and typically only for short periods. Weed eaters and large
mowers, 65 to 70 dBA at 100 feet, are a typical noise type of moderate
durations, depending upon the size and type of material to be mowed.
Herbicide applications in-channel use a truck-mounted tank with a small
gasoline powered pump. Noise levels for the pump are similar to noise from a
lawn mower: 65 dBA at 100 feet (page 2000-7, California Department of
Transportation, Division of New Technology, Materials and Research,
Technical Analysis Notes, 2nd Draft March 1991).
Because these activities are temporary, they are not considered significant.
The following BMPs will provide notice and reduce intrusiveness to neighbors.
,p>
| 4.1 |
Notify Local Governments of Scheduled Work |
| 4.2 |
Minimize Disturbances to Surrounding Neighborhoods |
4) Bank Protection
Noise levels recorded were sampled for typical bank protection activities
such as a truck unloading rock, an excavator placing the rock in the stream
channel, and a water truck pumping up the excess silted water from the channel
bottom. Noise levels ranged from 68 to 73 dBA at 100 feet with both the truck
unloading and the excavator working. Given standard attenuation, noise levels
within 50 feet of working equipment would be 74 to 79 dBA. Bank protection
work, such as the placement of riprap, has a wide range of progression from 40
to 200 feet per day depending on the difficulty of the characteristics of the
channel. The standard 60 foot wide lot within 50 feet of riprap placement
would experience the highest noise levels for 3 to 10 hours depending on the
difficulty of the project. Noise levels would decrease as distance doubles and
would further decrease if there is intervening vegetation between the residence
and the heavy equipment.
According to the CEQA Guidelines, if a project or plan would "increase
substantially the ambient noise levels of adjoining areas," the effect is
considered significant. Based on the measurements taken and the close
proximity (less than 50 feet) between heavy equipment and residential property
boundaries, sediment removal and vegetation management activities could
increase ambient noise levels by 3 dB or more at the residences in areas where
the DNL currently approaches the "satisfactory" standard, or could cause the
interior noise levels to exceed 45 dBA when windows in the residence are
closed (exterior noise levels would exceed 65 dBA). These increases would be
of short duration, typically less than one day to a few days at any given
location. Bank protection work would usually be singular occurrences over the
life of the program while some sediment removal operations are scheduled to
repeat two or three times over the twenty year project.
Even though the levels experienced at nearby residences could exceed
thresholds of significance for noise impact, the project impact would not be
considered significant because of the short duration of the noise increase. In
addition, the work, particularly erosion repair work, is done in many instances
at the request of the homeowner. If the adjacent homeowner views the work as
a benefit in protecting his or her property, the intrusiveness of any noise impact
may be lessened.
Because these activities are temporary, they are not considered significant.
The following BMPs will provide notice and reduce intrusiveness to neighbors.
| 4.1 |
Notify Local Governments of Scheduled Work |
| 4.2 |
Minimize Disturbances to Surrounding Neighborhoods |
5. Public Services and Utilities
a. Setting
Many of the urban stream channels now have or will be developed to have
recreational access and trail systems. More people are taking an interest in
urban creeks, and environmental education is taught at many schools, using
local creeks as subjects. The District recognizes this trend and cooperates with
recreation providers.
Stream channels, especially in the urban areas of the District, are crossed
with pipelines, cables and other delivery systems of utilities to consumers.
Many of the bridges that cross over streams link utilities from one side of the
stream to the other.
b. Significance Criteria
A project would be normally considered to have a significant effect on
public services if one or more of the following factors were met (CEQA
Guidelines):
Criterion Pub-1 Result in a prolonged temporary or a permanent deterioration in
the quality of existing recreational uses along stream corridors
used for walking and outdoor passive recreational activities.
Criterion Pub-2 Result in demands for public services or utilities that exceed
service capacities and would require additional facilities, staff or
equipment in order to maintain acceptable service ratios,
response times or other performance objectives--related to fire
protection, police protection, schools or parks.
Criterion Pub-3 Cause prolonged interruption to utility services due to
construction, i.e. interruption of service for longer than 8
hours.
Criterion Pub-4 Result in wastewater flows that exceed sewer line or treatment
plant capacity, contribute substantial increases in flows to
existing impacted sewer lines or require substantial expansion of
wastewater collection or treatment facilities, the construction of
which would cause significant environmental effects.
Criterion Pub-5 Exceed wastewater treatment requirements established by the
RWQCB.
Criterion Pub-6 Result in water demand that exceeds capacity of the water
supply or infrastructure system or would require substantial
expansion of water supply, treatment or distribution facilities,
i.e. project demand exceeds capacity.
Criterion Pub-7 Generate solid waste in area served by a landfill with limited
and/or insufficient permitted capacity to accommodate the
project.
Criterion Pub-8 Result in non-compliance with federal, state and/or local
statutes and regulations related to solid waste.
c. Impacts
Residential land uses are the most potentially sensitive to such annoyance
effects because the residents are there year-round, as much as 24 hours per day,
as compared to park lands where visitors are transient. However, in park lands,
the recreational experience is diminished if there is unwelcome noise, dust or
odor. Dust and odor have been discussed in the Air Quality section of this
chapter, and Noise has also been discussed in this chapter. In commercial or
industrial areas, the occupants are both there for only the work day and are
often in enclosed buildings with non-opening windows that are relatively
insensitive to such annoyance effects.
The long term impacts of work on recreational land uses are parallel to the
visual impacts. If the visual impact is considered significant, then the
recreational impact may also be considered significant because the work may
then reduce the quality of the recreational experience. However, the impact of
the routine maintenance in designated parklands or along trail corridors would
be mitigated by the BMPs that are listed in the aesthetics section of this chapter.
The District's Maintenance program does not increase the demand for
neighborhood or regional park or recreational facilities. Because maintenance
activities do not permanently affect existing recreational facilities or uses, this
is not considered a significant impact. As is stated in Chapter II, Project
Description, average sediment removal construction periods are 10 days, though
they can last as long as 3 months. Vegetation management and bank protection
work average less than 10 days. Because most of these activities would be
performed during the weekdays, it is possible that these recreational facilities
would be accessible during the weekend when most recreationalists would be
present. This is not considered a significant impact.
While sediment removal projects may occur annually along the same reach
of stream corridors, routine maintenance periods as listed above will not result
in a prolonged temporary or a permanent deterioration in the quality of existing
recreational uses along stream corridors used for walking and outdoor passive
recreational activities.
The Stream Maintenance activities will not cause prolonged interruption to
utility services due to construction, nor will they result in demands for public
services or utilities that exceed service capacities. No new fire protection,
police protection, schools or parks would be necessary as a result of the
proposed program. Fire protection would be provided and improved by the
vegetation management aspect of the Stream Maintenance program.
The Stream Maintenance activities will not contribute to wastewater flows
and therefore will not exceed sewer line or treatment plant capacity, nor will
they require substantial expansion of wastewater collection or treatment
facilities.
Stream Maintenance generates dredged sediments, trash and debris, and
sometimes vegetation, which are disposed of at landfills. Green waste from
vegetation management activities is largely composted. While the local
landfills can accommodate the annual average of 80,000 cubic yards of
sediment, the District is undertaking a Solids Material Management Program
to develop and implement long-term strategies for managing its solid waste
materials. One of the purposes of this study is to reduce the amount of
sediment disposed at landfills by finding other appropriate and beneficial uses
of the sediment. Other beneficial uses of sediment which are being investigated
are: reuse for streambed or wetland restoration, and in construction.
Preliminary results on the feasibility of these other beneficial uses will be
available in the Summer 2001 (Uday Mandlekar, SCVWD, personal
communication, 3/5/01).
|