Flood Protection Project
|
||||||||||||||||||||||||||||||||||||||||||||||||||||
| Request by the District for Corps to restudy upstream Highway 280 |
Sep 1986 |
| Corps began Reconnaissance Study of upstream Highway 280 |
Oct 1988 |
| Final reconnaissance report |
Nov 1989 |
| Feasibility phase begun | Oct. 1999 |
| Final feasibility report approved by Corps' South Pacific Division | Feb 1998 |
| Final Chief of Engineers Report approved by Secretary of Army | June 1999 |
| Water Resources Development Act of 1999 (Section 101) authorized construction | Aug 1999 |
| Environmental Impact Report certified by district Board of Directors | Aug 2001 |
| Water Quality Certification received | Dec 2003 |
Corps Headquarters approved Limited Reevaluation Report |
June 2004 |
| Begin design on Reach 12 | Feb 2007 |
| Sign project cooperation agreement | July 2007 |
| Begin project construction on Reaches 10B and 12 | June 2008 |
| Begin construction on Reach 6 | June 2009 |
Corps is currently in the preconstruction engineering and design phase. Depending on federal funding in fiscal year 2007, construction on Reaches 10B and 12 could start as early as June 2008. Total project costs are approximately $230 million.
District has begun design on Reach 6. Anticipate Construction to begin in 2009.