E6: Upper Llagas Creek Flood Protection*
Preferred project: A federal-state-local partnership
This project continues a partnership with the U.S. Army Corps of Engineers (USACE) and the State of California to plan, design and construct improvements along 13.9 miles of channel. The project extends from Buena Vista Avenue to Llagas Road and includes West Little Llagas Creek in downtown Morgan Hill. The federally authorized preferred project protects the urban area of Morgan Hill from a 1% flood (100-year event) and reduces the frequency of flooding in surrounding areas. Construction includes channel modifications and replacement of road crossings. Valley Water continues to work with Congress to aggressively pursue federal funds to bring this project to full fruition.
Local-funding-only project
Construct flood protection improvements along Llagas Creek from Buena Vista Avenue to Highway 101 in San Martin (Reaches 4 and 5), Monterey Road to Watsonville Road in Morgan Hill (Reach 7a), approximately W. Dunne Avenue to W. Main Avenue (a portion of Reach 8), and onsite compensatory mitigation at Lake Silveira.
Project Information
The project is being constructed in several phases, each with specific sections (referred to as reaches on the map) where the proposed improvements will occur. Phase 1 was completed in April 2022, including creating a new wetland habitat at Lake Silveira and planting more than 45,000 native plants along the widened and deepened channel. In August 2024, Valley Water completed Phase 2A of the project, including constructing a 2,300-foot-long tunnel underneath downtown Morgan Hill. The final phase of the project, Phase 2B, is now under construction and expected to be completed in 2027. Details about Phases 1 and 2A are under the History & Background section of this webpage.
The Phase 2B mailer is available with details about the work scheduled for each of the four reaches where construction will occur.
Ribbon-cutting
Join Valley Water and its partner agencies to celebrate the completion of major flood protection improvements as part of the Upper Llagas Creek Flood Protection Project.
The event will take place on Monday, November 16, 2026, at 10:00 a.m., at the Corner of La Crosse Drive and Vineyard Boulevard.
ALTERNATE LOCATION:
Should inclement weather occur during the event time, please convene at the Centennial Recreation Center, 171 W. Edmundson Avenue in Morgan Hill.
With an El Niño winter anticipated and the potential for more intense storms, this final project milestone comes just in time—so let’s cut the ribbon!
Phase 2B: in construction through spring 2027
Phase 2B construction consists of approximately 1,900 linear feet of twin reinforced concrete box culverts (10 ft x 9 ft), creek modifications and excavation by widening and deepening, installation and modification of culverts at various street crossings, construction of an inlet basin weir split-flow structure to divert high creek flows, and support of existing bridges by underpinning. Valley Water will construct improvements on approximately eight (8) miles of Upper Llagas Creek, from US 101 upstream to Llagas Road. Construction will include creek widening and deepening, bridge/culvert construction, traffic control, utility coordination and relocation, construction of maintenance roads, and habitat enhancements. Construction is expected to be completed in spring 2027.
Valley Water begins construction of the final phase (Phase 2B)
Valley Water began construction on Phase 2B, the final phase of the Upper Llagas Creek Flood Protection Project, in September 2024. This phase includes improvements on approximately eight (8) miles of Upper Llagas Creek, from US 101 upstream to Llagas Road. Phase 2B is scheduled for completion in spring 2027. Once completed, approximately 1,100 homes, 500 businesses, and over 1,300 acres of agricultural land will be protected from the 100-year flood. After the project's completion, a three-year post-construction mitigation native plant revegetation period will follow.
Click here to see a video showing completed and on-going work activity. An article about the project was published in the Morgan Hill Times. Click here to read the article.
The project began its final season of in-channel construction, which will continue through the end of calendar year 2026. This work season includes flood-risk-reduction improvements along approximately 3 miles of West Little Llagas Creek, from Watsonville Road upstream (north) to Llagas Road in Morgan Hill. A copy of this season’s work mailer is available to download.
West Little Llagas Creek has been widened and deepened from Watsonville Road to Ciolino Avenue and from Hillwood Lane to Llagas Road. Neighborhoods near the creek were subject to the following:
- Noise from large construction equipment, haul trucks, and work crews moving within the creek.
- Dust will be generated by the excavation equipment and haul trucks. Water trucks will be used to minimize dust.
- Excavation equipment operating during the day. Trucks will cycle in and out of the creek as they are loaded with excavated material for transport. Road closures are not expected, but flaggers will guide trucks in and out of the creek.
- Public trail closures when work is performed along West Little Llagas Creek. Valley Water will monitor impacts from noise and dust and take the necessary measures to lessen them. Safety will be a priority as the trucks enter and exit work sites. Please use extra caution when walking or driving near the construction site.
Crews will work Monday through Friday from 7:00 a.m. to 8:00 p.m. and Saturdays from 9:00 a.m. to 6:00 p.m. Work on the Upper Llagas Creek Flood Protection Project has been progressing quickly as crews continue building the flood protection measures.
Temporary Closures of West Little Llagas Trail (portions through December 2026)
Through the end of the year, portions of the existing West Little Llagas Creek trail will be closed on both sides of the creek, from Watsonville Road to Spring Avenue, to accommodate creek widening and deepening activities. Portions of these public trails, starting between Watsonville Road and Edmundson Avenue, were reopened by the end of July. Public trails from Edmundson Avenue to Spring are currently closed for widening and deepening the existing West Little Llagas Creek. The public trails within this stretch of the creek will be repaved and tentatively reopened by the end of December. Though the trails are reopened, an hourly or daily closure may occur to complete final improvements, such as painting the trail center stripe and installing mitigation plantings along the creek banks.
Spring Ave. Closure (through November 2026)
Spring Avenue will be closed to through traffic (map) at West Little Llagas Creek through November 2026. Traffic headed to Monterey Road will be diverted to W. Dunne, Ciolino, or Cosmo Avenues. Crews have completed the construction of three 10-by-9-foot box culverts beneath Spring Avenue to replace the single, smaller, and under-capacity box culvert that currently conveys stormwater. Spring Avenue will remain closed through November to accommodate utility relocations. Valley Water has already improved the creek channel upstream of Ciolino Avenue (previous Phase 2A underground diversion tunnel construction) to better convey more stormwater and aims to provide the same update at this location.
