Valley Water awards replacement construction contract for the Coyote Creek Flood Protection Project
On Oct. 27, 2026, the Valley Water Board of Directors awarded a replacement construction contract for the Coyote Creek Flood Protection Project to Gordon N. Ball, Inc.
Initially, the board awarded the contract to Shimmick Construction Company, Inc. on July 24, 2026. However, Valley Water and Shimmick mutually agreed to end that contract.
Gordon N. Ball was the second-lowest bidder in the original solicitation, at $125,649,597, approximately 1% higher than Shimmick’s. The bid by Gordon N. Ball, Inc. was also approximately 17% lower than the engineer’s estimate.
Gordon N. Ball also built the first phase of Coyote Creek flood protection improvements, known as the Coyote Creek Flood Management Measures Project, which was completed in 2025.
The contractor transition has slightly delayed the start of construction, but the anticipated completion date remains October 2028. Valley Water’s priority is to advance the project and deliver flood protection for the community.
The project will help reduce flood risk along approximately nine miles of Coyote Creek between Montague Expressway and Tully Road in San José. This second and final phase will add just over three miles of floodwalls, self-raising passive barriers and earthen berms.
Once complete, the improvements will help protect homes, businesses, schools, parks and transportation infrastructure, including in disadvantaged communities, against creek flows like those experienced during the February 2017 flood.
During construction, one trail and three parks, Rocksprings, Selma Olinder and William Street, will temporarily close. Work at Selma Olinder and William Street parks will include floodwalls, earthen berms and self-raising passive barriers. The barriers remain flat during normal conditions and rise automatically during high-water events to help keep floodwater within the creek corridor.
Valley Water recognizes the community’s concerns about construction-related park closures. Closures will not begin in 2026 and are currently anticipated to begin in early 2027. More reliable scheduling information will be available once Gordon N. Ball, Inc. develops its initial construction schedule.
For more information about the project, including a Frequently Asked Questions document, a video in three different languages that shows how the passive barriers work, and updates for trail and park closures, visit the Coyote Creek Flood Protection Project webpage. The FAQ is available in English, Spanish and Vietnamese.