Traffic and Trail Impacts
From time to time our construction and maintenance projects require temporary road or lane closures, trail closures or similar impacts to vehicular or pedestrian traffic. Current and planned impacts will be noticed here.
Current Trail Impacts
West Little Llagas Creek Trail in Morgan Hill
From May 2026 and continuing through the end of the year, the West Little Llagas Creek trail in Morgan Hill will be closed on both sides of the creek from Watsonville Road to Edes Court to accommodate creek widening and deepening activities.
The trail section from Edes Court to Spring Avenue will be closed later in the summer of 2026 to allow crews to complete similar creek work from Edes Court to Ciolino Avenue.
While there may be periods when no work is occurring in the creek or near the trails, please DO NOT enter the closed trail sections, as they and the surrounding area could be unsafe for the public. Please note that Valley Water will be reconstructing these public trails before reopening them.
Stream Maintenance Program 2026
As part of our Stream Maintenance Program (SMP), Valley Water performs work along creeks across Santa Clara County every summer. Under the SMP, work is conducted annually to improve the environment, reduce flood risk, and keep our communities safe. For decades, our crews have been trekking into streams to remove sediment buildup, manage vegetation, clear trash and debris, and stabilize banks that have eroded during high-water flows. To download a copy of the 2026 SMP mailer, click here.
Current Traffic Impacts
Hale Ave and Wright Ave in Morgan Hill
From October 23, 2026, through November 6, 2026, Wright Avenue at Hale Avenue will be closed from 8:15 a.m. to 4:00 p.m. Wright Avenue will reopen at the end of each day and will be open on the weekend, with a potential closure on Saturday, October 31, 2026. Project crews will be grinding the road surface, paving new asphalt, installing car sensors, striping, and completing sidewalks. These day closures are necessary to complete and open Hale Avenue permanently.
Hale Avenue Update
Hale Avenue is currently anticipated to open on November 6, 2026. Inclement weather may cause operational delays or necessitate extending closure dates. All critical in-channel flood-protection work is complete and ready for potential El Niño storms. The remaining tasks include restoring the areas where the work was carried out and electrical work to be done by PG&E.
East Caribbean Drive in Sunnyvale
For public safety, traffic control will be in place on East Caribbean Dr. during soil delivery.
As a part of the Pond A4 Resilient Habitat Restoration Project, Valley Water’s contractor will be delivering soil to the project, on Caribbean Dr. between Moffett Park Dr. and Crossman Ave., on Wednesday October 14, 2026. The effort requires a temporary lane closure and Bay Trail detour from 7:00 a.m. to 5:00 p.m. Flaggers will be on site to navigate traffic and pedestrians. At the end of each workday, all lanes will be reopened for the evening commute.