Back to top

Lower Penitencia Creek Improvement Project

About This Project

The Lower Penitencia Creek Improvements Project is located within the City of Milpitas. The project’s study limit extends approximately one mile from the north at its confluence with Coyote Creek to the south at San Andreas Drive. (Download Project Fact Sheet)

The one mile study limit is indicated on the map to the right. This area of creek receives some of its water from Berryessa Creek. Construction has begun on improvements to Berryessa Creek that will bring more creek flows into this one mile stretch of creek. Lower Penitencia Creek must be able to carry this increased flow.

In its current condition, Lower Penitencia Creek does not have the capacity to convey the increased flow (the future one-percent flood event - also known as the 100 year event*). This project is necessary to maintain the current existing Federal Emergency Management Agency (FEMA) accreditation along the east levee located between California Circle and Berryessa Creek. At the completion of the project improvements for the Lower Penitencia and Berryessa Creek Projects, the Santa Clara Valley Water District will update the FEMA flood insurance maps accordingly.

*A 100-year flood, sometimes called a one-percent flood event, is a rare and large storm event which has a 1-in-100 chance of occurring in any given year.

Lower Penitencia Creek Improvements Project Map
Datapoints
Status
On Target
Phase
Design
Location
Milpitas, CA
Schedule
Start 2013 / Finish 2021
Funding
Water district's Watershed Stream Stewardship fund and California Department of Water Resources Proposition 1E grant
News and UpdatesNews and Updates
Reports and DocumentsReports and Documents
Environmental and Community BenefitsEnvironmental and Community Benefits
History and BackgroundHistory and Background
News & Updates

The Lower Penitencia Creek Improvements Project is in the design phase with 90% in progress. The anticipated construction start date is summer 2019.

  • The water district received a draft Streambed Alteration Agreement (SAA) from California Department of Fish and Wildlife (CDFW) in September 2018.
     
  • In March 2018, the water district submitted all the required permit applications from the various state and federal regulatory agencies. The permit process is currently ongoing and anticipated to be received by March 2019, which would allow project construction to be advertised in early 2019, with construction in summer 2019.
     
  • The water district is working on right-of-way acquisitions necessary for project construction. The water district anticipates to complete the right-of-way acquisition as well as encroachment permits and temporary construction easements from Caltrans and City of Milpitas by January 2019.
     
  • The Environmental Impact Report (EIR) for the Lower Penitencia Creek Improvements Project is final and available under the reports and documents.

 

For more information: 

Environmental & Community Benefits

The Santa Clara Valley Water District’s Lower Penitencia Creek Improvements Project, when completed, will increase the channel capacity to carry increased water flows from the Berryessa Creek Flood Protection Project.

Benefits

  • Maintain existing Federal Emergency Management Agency (FEMA) accreditation along the east levee located between California Circle and Berryessa Creek
  • Minimize the need for seasonal removal of sediment and non-woody vegetation, which minimizes future maintenance costs
  • Enhances stream habitat
  • Creates additional wetlands

Geographic Area of Benefit

                Milpitas, CA

History & Background

Lower Penitencia Creek channel improvements were constructed in 1955, 1962, 1965, and in the early 1980's. The existing channel within the project's reach was improved at multiple locations in the 1980s. The channel improvements consisted of various modifications to the creek to increase capacity. In the reaches north of the confluence with Lower Berryessa Creek, the channel was widened and levees were raised .

This project will prevent flooding from the channel caused by future larger flows from Berryessa Creek.*

* Flooding in nearby areas caused by another creek will be addressed in a separate project.

Thumbnail
Lower Penitencia Creek in Milpitas