Upper Berryessa Creek Flood Protection*
This project was done in partnership with the U.S. Army Corps of Engineers (USACE) to plan, design and construct flood improvements to protect homes in Milpitas and San José, as well as Silicon Valley’s commercial district, from a 1% (100-year) flood flow. The Bay Area Rapid Transit (BART) 10-mile extension project spans from Warm Springs Station in Fremont to the North San José Berryessa area. The new Milpitas Station is underground and is located in the Berryessa Creek floodplain. The completed Berryessa Creek project is critical to the operation and public use of the BART station.
*This project was voter-approved as part of the 2012 Safe, Clean Water and Natural Flood Protection Program.
In 2018, Valley Water and the United States Army Corps of Engineers (USACE) completed the Upper Berryessa Creek Flood Protection Project. The project extended along Berryessa Creek for approximately 2.2 miles, from I-680 downstream to Calaveras Boulevard. This area is now protected against a 100-year storm event. A 100-year storm event has a 1% chance of occurring in any given year (a 1 in 100 chance).
Valley Water and USACE developed a Floodplain Management Plan (FPMP). The purpose of the FPMP is to:
- Document potential measures, practices, and policies that could reduce the impacts of future residual risks of flooding associated with the project, and
- Help preserve flood protection levels provided by the project and enhance the natural values of the floodplain and creek.
The final FPMP is available for review.
June 2023: Valley Water provided the Post-Construction Stormwater Management Plan to the San Francisco Bay Regional Water Quality Control Board.
July 2023: Valley Water hired an environmental consultant to develop the Off-Site Mitigation Plan for the San Francisco Bay Regional Water Quality Control Board.
January 2024: The Pacific Gas and Electric utility located downstream of the Montague Expressway bridge was relocated.
January 2025: The San Francisco Bay Regional Water Quality Control Board issued a revised order for their Water Quality Certification permit that required additional mitigation planting increasing the planting acreage from 3 to 15 acres. In 2023, Valley Water and the Regional Board worked together to identify off-site areas for the additional mitigation planting.
January 2026: Valley Water is currently designing the mitigation planting sites and anticipates starting construction in August 2026. Plant installation will follow, starting during the rainy season from November to March 2027 and will take three years to complete by approximately March 2029. Following completion of the planting, maintenance and plant establishment work will continue until March 2034.
Valley Water and USACE are working to reconcile project costs and close out the project by the end of 2026.
May 2026