F8: Sustainable Creek Infrastructure for Continued Public Safety*
This project supports Valley Water’s long-term efforts to ensure that existing flood protection infrastructure continues to function sustainably and provide the level of service originally intended. The project includes: (1) assessing and prioritizing existing creek and watershed infrastructure; (2) preparing watershed and/or creek asset management plans; and (3) implementing recommendations of asset management plans.
Undertaking this project provides for adaptive management of existing infrastructure, ensuring infrastructure continues to provide flood protection and public safety as climate and other changes evolve.
Regnart Creek Rehabilitation Project
In FY24, Valley Water selected the Regnart Creek Rehabilitation Project, located along Regnart Creek between Festival Drive to Bubb Road in Cupertino, for design and construction under Project F8.
The project will provide a long-term solution to ongoing creek erosion by reducing the risk of bank failures, protecting nearby homes and infrastructure, stabilizing the channel, and improving sediment flow to minimize future erosion.
A feasibility study, completed in January 2024, found that significant incision of the creek bed had destabilized the creek banks and trees, increasing risk to adjacent properties and infrastructure. To address these issues, the project will provide a nature-like channel that restores historic bed levels and stabilizes creek-side slopes. Opportunities to enhance riparian habitat will also be incorporated in the design where feasible.
Current Project Status
The project is currently in the design phase. Valley Water is conducting surveys for topographic, right-of-way, and tree information; hydraulic modeling; field investigations; and geotechnical evaluations.
Information gathered during these efforts will be used to prepare the project's 60% design, including engineering drawings and technical specifications. Completion of the 60% design is anticipated by August 2026.
Valley Water plans to host a public meeting in summer 2026 to update neighbors on the project and its current design.
Following completion of the 60% design, the Valley Water will continue advancing the design, prepare environmental documentation, and obtain permits from local, state, and federal regulatory agencies. The overall design phase is expected to take approximately three years to complete.
Project background
Regnart Creek begins in the foothills of the Santa Cruz Mountains and flows through residential neighborhoods before joining Calabazas Creek.
During the winter storms of 2023, sections of the creek experienced significant erosion and bank instability. In response, Valley Water completed an emergency repair project in September 2023 between Bubb Road and the Union Pacific Railroad tracks. The emergency work stabilized the most critically eroded sections of the creek using large boulders.
While the emergency repairs addressed the most urgent and high-risk sections of the creek, they did not resolve the underlying causes of erosion along the creek. As a result, Valley Water initiated the Regnart Creek Rehabilitation Project to provide a long-term solution to the ongoing channel incision, bank erosion, and tree instability.
Regnart Creek is filled with trees and vegetation. These trees help stabilize and protect the banks, but they also pose a risk to the creek as they are increasingly on unstable, eroding banks. In some sections of the creek, the bank has eroded to the property lines of the surrounding homes. The rehabilitation project is being designed to integrate with the creek's natural landscape, resources, and landforms.
Completed F8 Milestones
- Stevens Creek Asset Management Plan. Completed May 2024.
- Regnart Creek Geomorphic Study. Initially completed February 2024; revised April 2024.
- Initiated Watersheds Asset Management Plan Update in October 2023. Remaining work on the Watersheds Asset Management Plan Update will be carried out under Asset Management Program.
- Initial strategic planning for a total of 19 creeks, to identify potential planning studies, asset management plans, infrastructure improvement projects, and/or to continue existing operations and maintenance management strategies. Completed August 2023.
- Assessed and prioritized all Valley Water-owned creeks. Completed January 2022.
- Developed a process for assessing, prioritizing, and identifying creek infrastructure improvement projects. Completed May 2021
June 2026